Updated project timetable:

  • 14th June 2018 – Council of Capital City of Warsaw adopts resolution introducing changes in the city budget to enable acceptance of construction design and submission of application to obtain a construction permit for the construction of Sinfonia Varsovia Centrum.
  • 11th July 2018 – Orchestra accepts construction design developed by Atelier Thomas Pucher.
  • November 2018 – provisional deadline to obtain construction design.
  • August 2019 – scheduled deadline for completion of tender documentation, including detailed designs by Atelier Thomas Pucher,
  • August 2019 – announcement of tender for the general contractor of the construction works.
  • April 2021 – completion of Stage I of construction works, entailing historical buildings located in the immediate vicinity of Grochowska Street – two pavilions and the main building.
  • November 2024 – completion of Stage II of construction works, entailing the remaining historical buildings (annexes), the concert hall, development of the grounds and the frame.